Imperial Beach Main Replacement Emergency Work

While on site, our team responded to an emergency water main burst that occurred after a regular day’s shift. At a different location from where our team was working, a leak was detected and the client was relying on HHCI’s onsite team members to locate where the leak was coming from. After completing 600 ft of trenching, it was determined that a burst of a lateral pipe was causing the leaking throughout the jobsite. With all hands onsite, our team was able to successfully repair the damaged lateral pipe and was able to have services running by 8:00 am the following day.

Key Work Features

  • 24-hour work day
  • Welded Trench Plates
  • Trenching 
  • Backfilling
imperial-beach-01
imperial-beach-02
imperial-beach-03
imperial-beach-04